Changes Clauses and the Request for Equitable Adjustment
The changes clause is the government's power to alter the work and the contractor's right to be paid for the alteration. Both halves have conditions, and the one that most often defeats a contractor is a short period for asserting the right after the order arrives.

The rule in short
A changes clause lets the contracting officer order changes within the general scope by written order, and obliges the contractor to proceed. If the change increases or decreases the cost or time of performance, an equitable adjustment is made. The contractor must assert its right to that adjustment within thirty days of receiving the order. Government conduct requiring work beyond the contract without a formal order is a constructive change, compensated the same way.
The changes clause does two things at once. It gives the contracting officer power to alter the work unilaterally, within the general scope of the contract, by written order. And it entitles the contractor to an equitable adjustment where the change increases or decreases the cost or the time of performance. The contractor must perform first and be paid afterward.
The scope of the power
The power is bounded by the general scope of the contract and by the categories the particular clause names. A fixed-price supply clause reaches drawings, designs and specifications where the supplies are specially manufactured for the government, the method of shipment or packing, and the place of delivery. A construction clause reaches changes in the work within the general scope. A cost-reimbursement clause and a research and development clause each have their own list.
Commercial acquisitions are different in kind. Under the commercial terms clause, changes are made only by written agreement of the parties. There is no unilateral power, which means a contractor performing a commercial contract is not obliged to accept a directed change at all, and an agency that insists on one is asking for a breach rather than exercising a right.
Thirty days, and what has to be said
Under the standard fixed-price clause, the contractor must assert its right to an adjustment within thirty days from the date of receipt of the written change order. The assertion is not the priced proposal; it is the statement that an adjustment will be sought. Contracting officers may receive and act on a proposal submitted before final payment, but the assertion should not be left to that later stage.
The construction clause and the several other variants each state their own period, and the periods differ, so the clause in the contract has to be read rather than remembered. Where a contractor believes it has been constructively changed rather than formally ordered, prompt written notice is even more important, because the government's first defense will be that it never knew extra work was being performed.
The single most valuable step after a change is accounting rather than legal. Open a separate charge number for the changed work on the day the order arrives, capture labor and material against it, and keep daily records of disruption. Contractors who reconstruct costs a year later are forced into total cost arguments that boards and courts view skeptically. The change order accounting requirements in the regulation exist for this reason, and the contractor is the party that suffers when they are ignored.
Changes nobody wrote down
A constructive change occurs where the contractor performs work beyond the contract requirements without a formal order, and the additional work is fairly attributable to the government. Two elements have to be shown: that the work was outside what the contract required, and that the government ordered it expressly or by implication.
The recurring categories are recognizable in the field. Defective specifications that cannot produce a conforming result. An agency interpretation of an ambiguous specification imposed on the contractor. Acceleration, where the government refuses an excusable extension and insists on the original date. Over-inspection, applying a standard stricter than the contract requires. Interference with performance or failure to cooperate. And nondisclosure of superior knowledge the government held and the contractor could not reasonably have obtained.
| Route | How it arises | Must the contractor proceed | Path to compensation | Notice |
|---|---|---|---|---|
| Unilateral change order | Written order within the general scope | Yes | Equitable adjustment under the clause | Assert the right within the clause period |
| Bilateral modification | Agreement of both parties | Yes, on the agreed terms | Priced in the modification itself | None; but watch the release language |
| Constructive change | Conduct requiring work beyond the contract | Yes, while asserting the position | Equitable adjustment, proved as a change | Prompt written notice, in practice essential |
| Cardinal change | An alteration beyond the general scope | No; performance may be refused | Breach damages rather than an adjustment | Immediate written objection |
| Commercial products change | Only by written agreement | Only if the contractor agrees | The agreed price | None |
| Differing site condition | A materially different physical condition | Yes, after notice | Equitable adjustment under its own clause | Written notice before the condition is disturbed |
What an equitable adjustment measures
The adjustment is the difference between the reasonable cost of performing the work as originally required and the reasonable cost of performing it as changed, plus a reasonable profit on the added work. It is not a windfall and it is not a penalty. Where the change reduces the work, the adjustment runs downward and the government is entitled to a credit.
Because the measure is cost-based, the cost principles apply to what is presented, and unallowable costs included in a proposal create exposure independent of the merits. The tests are set out in the three cost tests. Above the applicable threshold, certified cost or pricing data may be required to price the modification, and the threshold moves with periodic inflation adjustments rather than staying fixed.
Impact costs are the hardest element. Loss of productivity, trade stacking, out-of-sequence work and extended overhead are real and are compensable, but they require a causal narrative supported by contemporaneous records rather than an industry productivity study applied after the fact.
When an adjustment request becomes something else
A request for equitable adjustment is a negotiating document. It becomes a claim when it is a written demand seeking, as a matter of right, the payment of a sum certain, and above the statutory threshold it must be certified. That conversion changes the deadlines, the interest entitlement and the forum, and the mechanics are in claims, certification and the disputes process.
Two related situations use the same cost vocabulary. Where the government suspends or delays the work, the delay clauses provide an adjustment without profit on the delay element. Where the contract is ended early, the cost recovery runs through the settlement proposal after an early ending. And where a schedule slip is the issue, whether the delay is excusable determines everything, which is examined in cure notices, excusable delay and reprocurement costs.
Points to carry away
- A change order within the general scope must be performed; disagreement about price is not grounds to stop.
- The right to an adjustment must be asserted within thirty days of receiving the written order.
- A change beyond the general scope of the contract is a breach rather than a change.
- Government conduct requiring extra work without a written order is a constructive change.
- The adjustment measures the difference in reasonable performance cost, plus reasonable profit.
- A commercial products contract is changed only by written agreement of both parties.
Questions readers ask
Can a contractor stop work while the price of a change is negotiated?
No, if the change is within the general scope and the clause applies. The obligation to proceed and the right to an adjustment are separate, and a contractor that halts performance pending agreement on price is in default rather than in negotiation. The correct sequence is to proceed, give the required notice, segregate the costs of the changed work in the accounting records, and price the adjustment afterward. Suspending performance forfeits the stronger position rather than creating leverage.
How are the costs of a change proved?
Preferably by actual costs segregated at the time the changed work is performed, supported by daily records, timecards and purchase documentation. Where segregation was not possible, courts and boards have accepted a modified total cost approach, which requires showing that the bid was reasonable, that actual costs were reasonable, that the contractor was not responsible for the added expense, and that a more precise method is impracticable. The bare total cost method is disfavored and rarely carries a case on its own.
What is a differing site condition and how does it differ from a change?
On a construction contract, a differing site condition is a subsurface or latent physical condition at the site that differs materially from what the contract indicated, or an unknown physical condition of an unusual nature differing materially from conditions ordinarily encountered. It is handled by its own clause rather than by the changes clause, with its own prompt written notice requirement before the conditions are disturbed. The remedy is an equitable adjustment measured the same way.
Sources
- Acquisition.gov — FAR Part 43, Contract ModificationsTypes of modification, who may execute them and the change order accounting requirements.
- Acquisition.gov — FAR Subpart 43.2, Change OrdersIssuance of change orders, definitization and change order accounting.
- Acquisition.gov — FAR 52.243-1, Changes: Fixed-PriceThe scope of the change power and the thirty-day assertion requirement.
- Acquisition.gov — FAR 52.243-4, ChangesThe construction changes clause, including written orders and the notice period.
- Acquisition.gov — FAR 52.212-4, Contract Terms and Conditions: Commercial Products and Commercial ServicesThe bilateral-only change provision applying to commercial acquisitions.
- Acquisition.gov — FAR 52.236-2, Differing Site ConditionsThe separate route for site conditions that differ materially from those indicated.
- Acquisition.gov — FAR Subpart 15.4, Contract PricingWhen certified cost or pricing data is required to price a modification.
Lawwise is a publication, not a law firm. This article states general rules and cites its sources; it is not advice about any particular case, and the law differs by state and changes over time.
More in Government Contracts
The Debriefing and the Clock It Starts
An offeror excluded before award, or notified of an award in a negotiated procurement, may obtain a debriefing by written request made within three days of the notice. A required debriefing must disclose the evaluation of the offeror's own proposal, the awardee's evaluated price and technical rating, any overall ranking and the rationale for award. It may not disclose point-by-point comparisons. The debriefing date controls both the protest deadline and the window for the automatic suspension.
Sealed Bidding and Negotiated Procurement Compared
Sealed bidding is required where time permits, award will be made on price and price-related factors, discussions are unnecessary, and more than one bid is expected. Bids are opened publicly and award goes to the responsible bidder whose responsive bid is most advantageous considering price alone. Negotiated procurement evaluates proposals against stated factors, permits a competitive range and discussions, and allows an award to other than the lowest price where the solicitation says so.
The Settlement Proposal After a Contract Is Ended Early
On a convenience termination the contractor stops work, terminates subcontracts, protects and disposes of property, and submits a settlement proposal within one year of the effective date unless the period is extended in writing. Recoverable amounts include preparations and work done, initial costs, settlement expenses, subcontractor settlements, and reasonable profit on work performed. Anticipatory profit is not recoverable, and a loss contract carries no profit.


